Mumbai Metro
Line 2B · Yellow
Line facts
| Status | Partly running |
|---|---|
| Operator | MMMOCL (Maha Mumbai Metro Operation Corporation Ltd) |
| Length in service | 6.83 km |
| Stations in service | 6 in service · 20 planned on the full corridor |
| Opened | 2026-04-08 |
| Target | 2028-12-01 |
| Colour | #FFC600 |
| Status as of | 2026-10-18 |
Corridor: Maharashtranagar Mandale ↔ Andheri West.
Riding this line
This page records facts and sources — it does not publish fares or timetables. For current timings, fares and official apps, use the operator’s own channels:
- Maha Mumbai Metro Operation Corporation (MMMOCL) — official site
Partly running: the Mandale–Chembur section (6 stations, 6.83 km) is in service (opened 8 April 2026, extended to Chembur on 13 August 2026). The remaining corridor towards Andheri West is under construction, targeted December 2028.
Recorded source: MMMOCL (official) + Wikipedia + ixigo · status as of 2026-10-18.
Corridor sketch
Simplified sketch of this corridor on the network map. See all 20 lines.
Opened & targeted sections
- Diamond Garden → Maharashtranagar Mandale — Running · opened 2026-04-08 · 5.53 km · 5 stations
- Chembur → Diamond Garden — Running · opened 2026-08-13 · 1.3 km · 1 stations
- Andheri West → Saraswat Nagar — Under construction · target 2028-12-01 · 6 stations
- Saraswat Nagar → Chembur — Under construction · target 2028-12-01 · 8 stations
Stations on this line
In service — 6 stations
- Maharashtranagar Mandale
- Mankhurd
- Deonar
- Chhatrapati Shivaji Maharaj Chowk (Chembur)
- Deshbhakt N.G. Acharya Udyan–Diamond Garden
- Chembur
Under construction — 14 stations
- Eastern Express Highway
- Kurla (East)
- SG Barve Marg
- MTNL
- ILFS
- Income Tax Office
- Bandra
- National College (Bandra)
- Saraswat Nagar
- Khira Nagar
- Nanavati Hospital
- Indira Nagar (Vile Parle)
- Prem Nagar
- ESIC Nagar
Timeline
- 2026-04-08 — Opened: First section opened
- 2026-08-13 — Opened: Chembur to Diamond Garden
- 2028-12-01 — Target: Full line target
A target is a published plan, not a confirmed opening; each entry keeps the source recorded on this page.
Source
MMMOCL (official) + Wikipedia + ixigo. Retrieved 2026-10-18; status recorded as of 2026-10-18. Sketch geometry is simplified and not to scale.